What is Burndown Chart in Scrum

Categories:

Recommended

What is Burndown Chart in Scrum?

4-5 minutes

A burn down chart is a graphical representation of work left to do versus time. It is often used in agile software development methodologies such as Scrum . However, burn down charts can be applied to any project containing measurable progress over time.

Typically, in a burn down chart, the outstanding work is often on the vertical axis, with time along the horizontal. It is useful for predicting when all of the work will be completed. In the Daily Scrum the Development Team updates the Sprint Burn Down and plots the remaining work of the day. A burndown chart is almost a “must” have tool for a Scrum team for the following main reasons:

  • monitoring the project scope creep
  • Keeping the team running on schedule
  • Comparing the planned work against the team progression

Burndown chart and emotion

How to Create a Burndown Chart?

To create this graph, determine how much work remains by summing the Sprint Backlog estimates every day of the Sprint . The amount of work remaining for a Sprint is the sum of the work remaining for the whole Sprint Backlog . Keep track of these sums by day and use them to create a graph that shows the work remaining over time.

Burndown Chart Example

  • Duration: 5 days
  • Sprint Backlog: 8 tasks
  • Velocity : 80 available hours

Step 1 – Create Estimate Effort

Suppose your ideal baseline for using the available hours over the sprint. So in the simplest for this is the available hours divided by number of days. In this example, 80hours over 5 days equating to 16 hours a day. In order to create the project burn-down chart, the data needs to be captured as a daily running total starting with 80 hours than64 hours left 1 (80 – 16) at end of day, 48 hours left at end of day 2, etc.

Burndown – Estimate effort

Step 2 – Track Daily Process

The daily progress is then captured in the table against each task. It is important to remember that the value captured for each day is the estimated effort to complete the task, not the actual effort.

Burndown – Daily progress

Step 3 – Compute the Actual Effort

The total remaining effort needs to be captured at the end of each day. This is the total(sum) of all of the estimated time remaining at the end of each day.

Burndown – Actual effort

Step 4 – Obtain the Final Dataset

When the data is available, the project burn-down chart can be created. This is relatively simple using the line chart option available within Excel.

Burndown – Final dataset

Highlight the summary table that contains the daily total for baseline effort and estimated effort. You should also capture the heading of time period (Day 0, Day 1, etc).

Step 5 – Plot the Burndown using the Dataset

It is very simple to create a project burn-down chart as following, as long as you know what data you are tracking.

Burndown chart example